Files
taskplaner/.planning/STATE.md
Thomas Richter 27ed813413 docs: create milestone v2.0 roadmap (3 phases)
Phases:
7. GitOps Foundation: ArgoCD installation and configuration
8. Observability Stack: Prometheus/Grafana/Loki + alerts
9. CI Pipeline Hardening: Vitest, Playwright, type checking

All 17 requirements mapped to phases.
2026-02-03 14:41:43 +01:00

1.8 KiB

Project State

Project Reference

See: .planning/PROJECT.md (updated 2026-02-01)

Core value: Capture and find anything from any device — especially laptop. If cross-device capture with images doesn't work, nothing else matters. Current focus: v2.0 Production Operations — Phase 7 (GitOps Foundation)

Current Position

Phase: 7 of 9 (GitOps Foundation) Plan: 0 of 2 in current phase Status: Ready to plan Last activity: 2026-02-03 — Roadmap created for v2.0

Progress: [██████████████████░░░░░░░░░░░░] 67% (v1.0 complete, v2.0 starting)

Performance Metrics

v1.0 Summary:

  • Total plans completed: 18
  • Average duration: 3.3 min
  • Total execution time: 60 min
  • Phases: 6
  • Requirements satisfied: 31/31

v2.0 Target:

  • Phases: 3 (7-9)
  • Plans estimated: 7
  • Requirements: 17

By Phase (v1.0):

Phase Plans Total Avg/Plan
01-foundation 2 7 min 3.5 min
02-core-crud 4 15 min 3.75 min
03-images 4 14 min 3.5 min
04-tags 3 13 min 4.3 min
05-search 3 7 min 2.3 min
06-deployment 2 4 min 2 min

Accumulated Context

Decisions

Key decisions from v1.0 are preserved in PROJECT.md.

For v2.0, key decisions from research:

  • Use Grafana Alloy (not Promtail - EOL March 2026)
  • ArgoCD needs server.insecure: true for Traefik TLS termination
  • Loki monolithic mode with 7-day retention
  • Vitest for unit tests (official Svelte recommendation)

Pending Todos

None — ready for Phase 7 planning.

Blockers/Concerns

None.

Session Continuity

Last session: 2026-02-03 Stopped at: Roadmap v2.0 created Resume file: None


State initialized: 2026-01-29 Last updated: 2026-02-03 — v2.0 roadmap created